Progress of Major investment Projects

Date:2008-09-20
<DIV><B>Projects of urban and rural infrastructure</B></DIV>
<DIV><B>1.       </B><B>Urban infrastructure   </B></DIV>
<DIV>In the first half of this year, 141 projects were listed in the first set of urban construction plan, 69 of which were projects of continuation and 72 newly added projects. At the end of June, 71 projects were under construction with an investment of 2.874 billion yuan, accounting for 17.7% of the annual investment plan; Huluding Bridge, Qingzhu Flyover, the transformation of Qiyi Ditch were wholly or partly put into operation, while some projects were still under construction, including those of the infrastructure of ASEAN Business Zone, of comprehensive environmental treatment of Zhupaichong and of 5 bridges that would cross over Yongjiang River; the construction of some projects commenced one after another, including the ecological protection in Qingxiu Mountain as the sub-component of Nanning urban environmental improvement project with the loan issued by ADB, the comprehensive environmental treatment of Xinxu Stream and Keli Stream, Fengling South Road, Baihualing Road, the roads surrounding the east campus of No. 2 Middle School, Baiyun Road and Longteng Road; some projects were on the initial stage, including the city light rail, the infrastructure of the core area of Wuxiang New District, the step water conservancy projects in Yongning, the comprehensive environmental treatment in the urban and rural areas of Nanning with the loan issued by WB and Luban South Road; the projects for celebrating the 50thanniversary of the establishment of Guangxi Zhuang Autonomous Region were accelerated, including Guangxi Sports Center, Guangxi Museum for Nationalities and the new Guangxi Science and Technology Hall. Besides, the development and construction of tourist projects were accelerated, including Daming Mountain Tourist Resort, Qingxiu Mountain Tourist Resort and Southeast Asian Food Street, with the purpose of building Nanning into an excellent tourist destination, a food paradise and a shopping center, a modern city with the features of subtropical landscape and Zhuang people’s conventions and customs.</DIV>
<DIV> </DIV>
<DIV><B>2.       </B><B>Rural infrastructure</B></DIV>
<DIV>(1)    The constructing pilot projects for the new countryside made some progress: In 2006, Nanning began to construct pilot projects for the new countryside in Wuming County and former Yongning County, with a planned investment of 1.616 billion yuan within two years. By July 12, there were 1069 such pilots under construction and 5015 completed, finishing accumulated investment of 941 million yuan, taking up 65% of the plan.</DIV>
<DIV> </DIV>
<DIV>(2)    The planned investment of 486 million yuan will be put in the project of constructing infrastructure in Long’an County and Mashan County that are located in the stony mountainous area. By the end of June, however, 7309 items had begun and 4614 items had been finished, accounting for 77.7% and 49% of the total projects respectively, with an investment of 93 million yuan.</DIV>
<DIV><B></B> </DIV>
<DIV><B>Industrial projects</B></DIV>
<DIV><B></B> </DIV>
<DIV>1.   The campaign of a hundred industrial projects: altogether there are 150 projects planned to be constructed this year, including 50 projects of continuation and 100 newly added projects, with a total investment of 18.849 billion yuan, 4.759 billion yuan annually. By the end of June, there had been 108 projects under construction, including 61 new projects. Since 2005 when the campaign began, the aggregated investment has reached 3.772 billion yuan, 1.56 billion yuan of which was done in the first half of this year.<Br><Br></DIV>
<DIV>The major projects under construction made successful progress: The project of 2 new-type dry cement production lines with the daily production capacity of 4000 tons in Huarun Cement (Nanning) Co., Ltd. with a total investment of 655 million yuan, is now in the process of installing equipment; the project of bagasse pulp with the annul production capacity of 50,000 tons in Nanning Jinlang Pulp Company, with a total investment of 180 million yuan has finished the investment of 108 million yuan; the project of rolled tissues with the annual production capacity of 17,000 tons and paper tissues & paper products with the annual production capacity of 17,000 tons in Nanning Heng’an Tissue Co., Ltd. with a total investment of 363 million yuan, is expected to partly go into operation in August, completing an investment of 15 million yuan.</DIV>
<DIV> </DIV>
<DIV>The preliminary work of a number of major projects was timely pushed forward: The bamboo pulp and paper integration project with the annual production capacity of 98,000 tons of bamboo pulp and 120,000 tons of quality paper as well as a bamboo base of 300,000 mu under Wargain Paper Co. Ltd. with a total investment of 497 million yuan was approved, with its environmental impact assessment and the planning for construction land of use being approved and the permit of construction land of use obtained, and the document of land use for examination sent to Yongning Sub-bureau of National Land and Resources. The project is expected to commence in September; the developer of the project of Yuchai Nanning International Logistic Center and Xingning District Government together formed a land requisition team to conduct the initial investigation for the project and the work of land requisition, removal and compensation. The project is expected to commence in September; the project of the technology improvement of the production base of 200,000 kilowatt tubular unit with a total investment of 153 million yuan has been through with the initial work, such as filing the project on record, environmental impact assessment, examination and approval of project planning, master plan examination and approval, examination of the land use, plan designing, etc. The plan for the use of land has been submitted for approval, and it’s planned to begin construction in September.</DIV>
<DIV> </DIV>
<DIV>2.  Commercial and trade project: there are altogether 57 projects planned to be constructed this year with a total investment of 12.965 billion yuan, 55 projects under construction with a total investment of 10.054 billion yuan and 2 new projects just commenced with a total investment of 2.91 billion yuan. The number of projects with the total investment of less than 100 million yuan is 33 totaling 1.382 billion yuan; those projects with the investment of more than 100 million yuan are numbered 17 totaling 3.073 billion yuan; the projects with the investment of over 500 million yuan are numbered 3 totaling 1.8 billion yuan; the projects with the investment of more than 1 billion yuan are numbered 4 totaling 6.71 billion yuan. The investment for the commercial and trade projects in the first half of this year reached 1.192 billion yuan.</DIV>
<DIV> </DIV>
<DIV>3.  Real estate development project: by the end of June, there have been 266 development projects under construction. The real estate development companies plan to totally invest 72.877 billion yuan, 16.961 billion yuan annually. In the first half of this year, 8.091 billion yuan was invested, up 40.11%.</DIV>